Boiler cascade systems are a familiar sight in commercial plant rooms and can offer significant advantages over a single large boiler where heating demand varies considerably, and where smaller individual boilers may be easier to manoeuvre into place. In practice, a well-designed, quality cascade should be straightforward to specify, install and control, if you choose wisely.
Start with the load
The starting point when designing a cascade should always be the building’s heating requirement rather than how many boilers can fit in the plant room. Although installing multiple boilers enables high outputs to be achieved, one of its greatest advantages is the ability to respond more closely to changing loads.
A commercial building rarely needs its full design heating output all of the time. Demand can change substantially according to outside temperature, occupancy and how different areas of a building are being used. A single large boiler is limited in how far it can turn down its output. During periods of low demand, its minimum output may still exceed the load on the system.
When several smaller boilers operate in cascade, they can be brought online or taken offline as demand changes. This provides a greater overall modulation range and allows the system to match the load more closely, particularly under part-load conditions.
Use configuration tools
The next consideration is how the cascade will physically come together. There may be different boiler combinations, hydraulic separation options, headers, frames and accessories to consider, alongside the practical constraints of the plant room itself.
Well-designed online configuration tools make the process of cascade system design and product selection much easier by taking you through the available options in a logical sequence. Ideal Commercial Heating, for example, has separate Cascade Configurators for its Evomax 2 wall-mounted and Imax Xtra 2 floor-standing boiler ranges which will generate a complete cascade package, including a schedule of the components.
Prefabrication simplifies installation
Good quality prefabricated frame and header kits should reduce the amount of measuring, cutting and fabrication required on site. The difference can be considerable in the time spent building a cascade. Using Ideal Commercial Heating’s prefabricated frame and header kits, a three-boiler Evomax 2 cascade can be assembled in under 90 minutes.
Cascade controls don’t necessarily mean a complicated BMS upgrade
Good control is fundamental to an effective cascade. The boilers need to know when to fire, in what sequence and at what output so that the required load is met efficiently.
A Building Management System (BMS) can certainly control a cascade, but it is not the only option. Increasingly, sequencing functionality can be provided at boiler level. With the Evomax 2, for example, a Varican plug-in control card enables boilers to be linked and sequenced without requiring a complex BMS purely for boiler cascade control.
Design for servicing and resilience
Resilience should be designed into the installation. Consider how individual boilers will be isolated, how easily engineers will be able to reach components for servicing and what proportion of the building’s heating requirement can still be met if one appliance is unavailable. Boiler rotation can also help share operating hours across the cascade rather than repeatedly relying on the same lead boiler.
This is also where product quality and long-term manufacturer support matter. A commercial heating system needs to remain reliable throughout its working life. Good access for maintenance, dependable controls, readily available components and technical support all contribute to long-term performance.
Ultimately, there is more to a successful boiler cascade than connecting several appliances together. The best systems start with an accurate understanding of the load, use the available tools to simplify specification, take advantage of prefabrication, adopt an appropriate control strategy and consider servicing and resilience from the beginning. Get those elements right and a cascade can be a straightforward way of delivering flexible, efficient and dependable commercial heating.
idealcommercialboilers.com
Charlie Mowbray is Senior Product Manager at Ideal Commercial Heating.